Tennessee’s TMDL Program is a part of Water Pollution Control’s Watershed Management Section. The development of TMDLs follows the schedule established as part of the
1998 agreement between EPA and TDEC,
which is based upon the 1998 303(d) List
| YEAR | CUMULATIVE PERCENTAGE | CUMULATIVE TMDLs |
|---|---|---|
2002 |
5 |
40 |
2003 |
10 |
80 |
2004 |
16 |
120 |
2005 |
20 |
160 |
2006 |
25 |
200 |
2007 |
40 |
319 |
2008 |
55 |
438 |
2009 |
70 |
557 |
2010 |
85 |
676 |
2011 |
100 |
792 |
Tennessee uses a 5-step approach in the TMDL process:
Identify Water Quality-Limited Waters
Prioritize Water Quality-Limited Waters
Develop the TMDL Plan
Implement Water Quality Improvement Actions
Assess Water Quality Improvement Actions