 Statewide Student Management System (SSMS)
Implementation Status Update as of 11/18/05
Phase I & II: Seventy-two school districts, three State Special Schools and the Department of Children’s Services are in various stages of live implementation of the SSMS (StarStudent and EasyIEP) during the 2005-06 school year. Phase II districts are in the process of completing data conversion and training related to the Academic History module, the last component of the implementation process.
Phase III: Twenty-six school districts are scheduled to come onboard for the 2006-07 school year. Welcome Packets have been distributed that outline the training plan and data conversion process for StarStudent.
- The Project Team conducted three regional Phase III Kick-Off sessions across the state during the week of November 14, 2005 that provided the districts with an overview of the implementation rollout plan for data conversion and training, including a timeline and the expectations for making the transition to StarStudent and EasyIEP.
- Introductory DBA (Database Administrator) WebEx training will begin on November 29, 2005 followed by more detailed regional training for DBA’s beginning in January of 2006.
- These districts will begin scheduling training in January 2006 in preparation for scheduling students into SSMS for the 2006-07 school year.
- Regional training sessions for EasyIEP administrators and end users are scheduled to begin in January 2006 as well.
- Additional StarStudent training will occur later in the school year and into the summer.
- The initial preparation for the data conversion process (conference calls with each district) began in November as well.
Phase III Districts
PHASE III |
These districts will ‘go live’ in July/August 2006. |
Anderson
Athens
Blount
Bradley
Campbell
Carroll
Carter
Clinton
Decatur |
Franklin Special
Grundy
Humphreys
Lake
Lawrence
Marion
McMinn
Morgan
Murfreesboro |
Oneida
Richard City
Robertson
Rutherford
South Carroll
Stewart
Sullivan
West Carroll |
|